May 2003: Visit to Cinderhill Spur - tram derailed
during visit
June/July 2003 County Council Members Special Meeting
Summer 2003 Design Consultation by NET
Summer 2003 Government Funding Decision by the Department for Transport
Autumn 2003 Full Councils meet; Final decision by County Council to approve
or reject Tram extensions.
Autumn 2003 Application by NET for TWAO (Transport
and Works Act Order)
Spring /Summer 2004 Public Inquiry
2005 Secretary of State Decision
Late 2005 Planned Start of Construction
2008 Planned System Opening
It is expected the full Councils will not meet until summer 2004 to consider
the Environmental Impact Assessment reports. Therefore it is possible
that each limb of the timetable thereafter will be delayed by anything
up to 12 months. As further information becomes available, this page will
be updated.
|